- After fixing the first layer of drywall, the seams between sheets are filled with joint compound to strengthen the structure. If the seam is not along a factory edge (that is, where the sheet was cut manually to fit size), such an edge requires additional preparation. In this case, a bevel is cut along the edge — at about a 45° angle, to a depth of roughly one‑third of the sheet thickness. This operation is best done before installing the sheet on the frame to ensure more accurate and neat finishing. Recesses from screws in the first layer do not need to be filled, since they will be covered by the second layer of drywall.
- The second layer of drywall is fastened in a staggered pattern relative to the first, so that seams do not align. The minimum offset is 400 mm. Sheets are screwed with spacing no greater than 250 mm. Screw recesses and seams between sheets are filled with special non‑shrinking joint compound, reinforced with tape. Gaps at the floor and ceiling (where the 10 mm offset was left) are filled with construction foam. Seams adjoining walls are filled with non‑shrinking compound and reinforced with tape.
After completing all the steps described above, we obtain a plane assembled from drywall sheets with seams filled with joint compound. This type of preparation can be classified as
Q1 level, but only if the work is done properly and defects do not exceed acceptable limits.
At this stage, the following are permissible:
- Vertical deviations — no more than 3 mm per 2 linear meters
- Putty ridges — no more than 2 mm
- Scratches, dents, gouges — no more than 3 mm
- Shadows from side lighting are possible
To achieve
Q2 quality, seams are additionally leveled. The goal here is not just closing joints but creating a smoother and more uniform surface.
First, protruding ridges of compound are removed with abrasive paper (P120). Then these areas are primed with penetrating or strengthening primer to improve adhesion. After that, a leveling layer of gypsum or polymer putty is applied with a wide trowel (40–50 cm). Once dry, the surface is sanded with P180.
This wide layer smooths transitions and makes the surface more even, so seams gradually “fade out” into the sheet plane. This reduces the chance that joints will be visible under final coatings.
At this stage, the following are permissible:
- Vertical deviations — no more than 2 mm per 2 linear meters
- Putty ridges — no more than 1 mm
- Scratches or tool marks — no more than 1 mm
- Shadows from side lighting may remain
To achieve
Q3 quality, all Q2 steps are performed, then the entire surface is primed and covered with a continuous layer of gypsum or polymer putty. After drying, sanding is done with P120 and P180 abrasives.
At this stage, the following are permissible:
- Vertical deviations — no more than 1 mm per 2 linear meters
- Sanding scratches — up to 0.3 mm deep
- Gaps in filled seams — no more than 0.3 mm
- Minimal shadows from side lighting
Not allowed: visible dents, scratches, gouges, tool marks, or local ridges of compound.
To achieve
Q4 quality, all Q3 steps are performed, then the surface is primed with strengthening or penetrating primer and a 0.5 mm layer of polymer putty is applied. After drying, sanding is done with P240 and P320 abrasives.
At this stage, the following are permissible:
- Vertical deviations — no more than 0.5 mm per 2 linear meters
Not allowed: visible dents, scratches, gouges, tool marks, sanding scratches, ridges of compound, or shadows from side lighting.
From Q4 requirements we see that tolerances are fractions of a millimeter. Even minor mistakes during frame assembly or sheet installation can turn a 0.5 mm deviation into 1 mm, resulting in Q3 instead of Q4.
It is especially important to understand that cracks at drywall seams are unacceptable at any level — from Q1 to Q4. Therefore, installation rules must be strictly followed from the start, and saving on materials or components is not acceptable. If the problem lies in poor‑quality profiles or fasteners, it cannot be corrected with extra putty; the entire structure must be dismantled and rebuilt.
In other respects, drywall preparation is similar to leveling with plaster and putty. Q1 creates a flat plane with deviations up to 3 mm per 2 meters, and each subsequent level gradually improves quality step by step until Q4.
Thus, we have fully reviewed the preparation of rough walls to different Q levels. Now you know not only the differences between each level but also the properties of bases and materials used to achieve them.
In the next lesson, we will move on to analyzing surface defects and wall inspection.